Project Profile: Lake Vermont Mine

Project Start Date: 3rd Quarter 2008 (Q1 FY 2009)

Project Finish Date: 1st Quarter 2009 (Q3 FY 2009)

More Photos

Plant Description

  • 5.6Mt/a ROM(as)
  • 800t/h two stage size reduction system(as)
  • 800t/h raw coal processing plant(as)
  • Reclaim and load trains at 4250t/h(nom)
  • Coarse rejects and tailings co-disposal system

Client Need

Design, construct and commission a coal handling and preparation plant to process coal from a resource of 103 million tonnes in the Bowen Basin at Lake Vermont approximately 15 km northeast of Dysart

Solution

A CHPP design that:

  • Produces saleable coal with the following target specifications:
    • Coking Coal: 7.5% ash (ad), 11.5% moisture as shipped;
    • PCI Coal: 9.8% ash (ad) at not greater than 8.5% total moisture (as);
  • Minimises fines generation and required manning levels.
  • Is robust for its 20 year design life, is safe and easily maintainable.

Outcome

  • The Lake Vermont CHPP was designed, constructed and commissioned within the required project timeframe and budget.
  • The commissioning phase was completed ahead of schedule and despite the very tight time frame was completed without an isolation incident.
  • The CHPP project reached Practical completion 2 weeks ahead of schedule and since has passed the 14 day throughput trial component of the CHPP Performance Test.
Lake Vermont Mine